Construction has started on the $123 million Cortez Bridge replacement
The Cortez Bridge replacement by the numbers
- $123 million
- for the replacement project
- 65 feet
- tall for the new fixed span
- 1,200 days
- the project is expected to last, approximately
- 0.9 miles
- of bridge and roadway approaches
Sources: Beacon Media, The Bradenton Times
If you cross to Anna Maria Island, your commute is about to change. Crews broke ground Nov. 16 on a 65-foot-high fixed span on S.R. 684 (Cortez Road) that will replace the drawbridge built in 1956.
Crews work 7 a.m. to 6:30 p.m., with occasional night and weekend work, so expect lane and shoulder closures. In the first phase, traffic shifts slightly south at both approaches. We suggest leaving extra time.
- Finish: expected summer 2030
- Staging site: former Seafood Shack property, owned by Manatee County
- Boaters: Intracoastal Waterway stays open; drawbridge schedule unchanged
- Approaches: Gulf Drive to 123rd Street West in Cortez
Crews will build the new bridge in two phases
| Phase | Work |
|---|---|
| Phase 1 | Build north half, then shift traffic |
| Phase 2 | Demolish old bridge, build south half |
Sources: Beacon Media, The Bradenton Times
Cortez business owners are weighing hope against worry. Max Tanski of The Fox Mercantile backs the new bridge but said he was “shocked by the traffic not in season.” His pitch to customers: “There are two bridges, so come on by.”